Office Renovations - Cont. 2
The drywall taper was in today to start the job of seaming the drywall. The first coat of compound was applied. The taping is expected to be completed by the 29th.

April 24
Picked up yhe ceiling tiles for the suspended ceiling. The decision to install a suspended ceiling was based on some pre-existing electrical junction boxes that would require rewireing other areas of the house to eliminate. The suspended ceiling will allow access to the ceiling area in the future for any services that need to be worked on.
The ceiling tiles are made of MDF (Medium Density Fibreboard) are are meant to be painted or stained. The ceiling grid is a system called CeilingMax, a new product is surface mounted to the joists (doesn't require a drop between the joists and the tiles).