Office Renovations - Cont. 3

The drywall taping is now complete, the drywall primer/sealer has been applied and the first coat of colour has been applied.


May 3
The second and final coat of paint has been applied,  The ceiling grid has been installed in the closet and the ceiling tiles have been cut and temporarily installed.  The ceiling tiles will be removed for painting and to have the pot lights installed.  The installeation of the grid in the office has started.


May 4
The main field of the ceiling grid in the office has been installed.


May 8
Ceiling grid complete, perimeter ceiling tiles cut, pot lights installed, electrical tie-ins complete.